BACKWARDS PATH

CRITICAL PATH ANALYSIS

A backward pass in the area of project management refers to the calculation of late finish dates and late start dates for the portions of schedule activities that have not been completed. This is determined by starting at the project's scheduled end date and working backwards through the schedule network logic

MANDATE

5WEEKS

3 8 3 8 0

PLAN

2WEEKS

8 10 11 13 SLACK

HLR

6WEEKS

13 19 13 19 SLACK

KICK OFF

3WEEKS

0 3 0 3 SLACK

BUSINESS C

5WEEKS

8 13 18 13 SLACK

DEPLOY

1WEEK

19 20 19 20 SLACK

BRIEF

1WEEK

3 4 6 7 SLACK

BRP

8WEEKS

4 12 7 15 SLACK

SIGN OFF

4WEEKS

13 17 15 19 SLACK
ES = Earliest start
EF = Earliest finish
LS = Late start
LF = Late finish

Duration = Planned Task Time

Slack = if slack is 0, it’s a critical task

Slack = LS – ES OR LF – EF

3rd Calculate Slack