CRITICAL PATH ANALYSIS

The term forward pass refers specifically to the essential and critical project management component in which the project team leader along with the project team attempts to determine the early start and early finish dates for all of the uncompleted segments of work for all network activities

MANDATE

5WEEKS

3 8 LS LF SLACK

PLAN

2WEEKS

8 10 LS LF SLACK

HLR

6WEEKS

13 19 LS LF SLACK

KICK OFF

3WEEKS

0 3 LS LF SLACK

BUSINESS C

5WEEKS

8 13 LS LF SLACK

DEPLOY

1WEEK

19 20 LS LF SLACK

BRIEF

1WEEK

3 4 LS LF SLACK

BRP

8WEEKS

4 12 LS LF SLACK

SIGN OFF

4WEEKS

13 17 LS LF SLACK
ES = Earliest start
EF = Earliest finish
LS = Late start
LF = Late finish

Duration = Planned Task Time

Slack = if slack is 0, it’s a critical task

Critical path = Any task with 0 Slack

LF = Highest LS Predecessor
LS = LF - Duration

2nd Calculate LF + LS in a backward path